Pondtail Wood – Update Week Ending 8th July 2016

No activity has taken place in Pondtail Wood this week

 

Key dates

 

  • Stop Notice was served on the 13th June 2016 and took effect immediately.
  • The Enforcement Notice was served on the 13 June and will take effect on 12th July 2016.
  • Remedial work specified in the Enforcement Notice must be completed by 23rd August 2016

    (42 days from when the notice takes effect).

  • Before 30 April 2017 the land must be restocked with trees as per the Forestry Commission Notice.

 

SDNPA Website

 

SDNPA website has a dedicated webpage with regular updates at:

 

https://www.southdowns.gov.uk/stop-notice-and-enforcement-notice-issued-at-pondtail-wood/